Question 5
- Base plate;
- toe board;
- guard rail.
- 
        
(a) Sketch a section through an independent scaffold and label the following members:
(b) list five stages involved in applying pebble dash finish to sandcrete 
        blockwork.
(c)State two reasons for sourcing capital for the operation of a building Materials venture.
Observation
Most candidates were able to:
- list five stages involved in applying pebble dash finish to a sandcrete blockwork;
- state two reasons for sourcing capital for the operation of a building materials venture.
However, few of them were unable to state one  function each of base plate, toe board and guard rail parts of a tabular  scaffold.
      5        (a)  Functions of parts of a scaffold
    (i) Base plate:    To provide a firm base for the standard.
    ( ii) Toe-board:
    -     To prevent the foot of workmen from slipping off the platform.
    -     To prevent materials from falling off the platform
    -     To prevent tools from falling off the platform 
    (iii)  Guard rail: To prevent workmen from  falling off the platform.
    (b)    Five  stages involved in applying pebble dash
- get the materials, i.e pebbles and rendering mortar ready;
- prepare the wall surface, i.e cleaning, wetting or dampening;
- apply the rendering mortar (i.e., first and second coats);
- float and trowel the mortar for even surface;
- throw and press the pebbles into the rendered wall surface.
(c) Reasons for sourcing capital:
- for the expansion of the business;
- To meet customers’ demand
- To stabilize the business
- To increase profit margin.